Together Nifes Consulting and Rural Energy created a holistic solution that included two 990kW Herz industrial biomass steam boilers to provide steam to power both the manufacturing process and heat the plant.

This large scale project involved the build of a brand new steel framed plant room to house the new boilers, a two-storey office complex, two new flues and fuel delivery system. As principle contractor, Rural Energy was also responsible for keeping the site operational - carefully managing the removal of the old wood boiler and switch over to the new Herz boilers whilst keeping the process steam operating.

The primary source of fuel for the boilers included sawdust and timber waste generated by the manufacturing plant. In collaboration with Nifes and JELD-WEN, Rural Energy designed a system that would meet new emissions standards and suit the manufacturing plant. The large steam boilers were customised to include a specially designed moving grate combustion chamber, modified to suit dusty fuel. With a continuous self-replenishing fuel source, a large shredder was also installed at the factory to enable the reject wood and timber waste product to be chopped up and transported to the main silos for storage.

The project is now in its final stages with the site now being commissioned and completion planned for the end of October.

This new system will help JELD-WEN to improve its sustainability credentials reducing both their particulate emissions and carbon footprint. In addition the company will also benefit from a cut in their running costs as well as an additional income from the Renewable Heat Incentive (RHI) scheme.

waste-wood-legislative-framework-img

Download Our Technical Update

Download Previous Updates:

News

feature image
New build residential solar PV
by Paul Clark, September 30 2025
Project Update | Narberth We’re proud to be delivering a major renewable energy installation at the Narberth development – a large domestic scheme...
feature image
I’m thrilled to be speaking at #IMHX!
by Paul Clark, September 9 2025
Following the success of the UK Warehouse Association 2022 Solar Toolkit, an updated and enhanced edition is being launched this week. This...
feature image
New generation connections are being managed more closely
by Paul Clark, August 14 2025
Navigating DNO Connection Offers: Why Timing is Critical for PV Installations When developing a site for a new photovoltaic (PV) installation, one of...