PV - 10x Academy Schools

PV - 10x Schools for an Academy Trust

 

Sector: Educational
Technology: Solar PV
System size:

465 Kw peak [1084 panels] Over 10 Schools

Install type:  Roof mounted panels
Estimated Annual Generation: 414,360 kWh/yr
Location: Midlands
Contract scope:
  • Site survey
  • System PV size optimisation
  • System electrical design
  • Full turn key installation
Click the TAGS below to see more similar case studies
IMG-20231030-WA0020

Client Needs

The current electricity cost in the schools has increased hugely recently due to current economic situation and has become difficult to manage. The client needed a solution to reduce the electricity cost across their portfolio. The savings from electricity bill can be utilised elsewhere accross the sites.

The solution and its installation must not be disruptive to the day-to-day running of the schools so we had to work very closely with each of the schools staff.

WhatsApp Image 2023-10-31 at 14.07.47_e31f7ece

Project Solution

The Solar PV system includes the following:

Roof mounting frames, for sloped and/or flat roofs, depending upon each site. 

The operations were planned around a site set up and scaffolding over the weekend, deliveries on the following Monday, and site indusction and installation start on the Tuesday. Each week we worked on a different school so the planning behind the scenes was extremely important  so the flow of work was not interrupted. 

1084 PV Solar panels are installed over the 10 Schools accross the Midlands. The estimated Annual power generation over 10 schools is 414,630 Kw per year. This generation will reduce the carbon emissions by approx. 80,240 kg/yr.

rzeDzeZcwdvrbiGhqkIffEi8he2Cpv642gTzjhcdfg4=_plaintext_638344408396417984

Project Solution

Our client came to us directly, looking to reduce their electrical costs and also reduce their carbon footprint.

 

Hoddgetts - Tower

Services Provided in this Project

Whilst most solar PV systems are custom installations, there are some standardised products that we regularly take care of for our clients.

  • Remote Technical Support
  • Tailored Service & Maintenance
  • Spares & Consumables
  • Emergency Response
  • PV System Performance Monitoring

WhatsApp Image 2023-11-01 at 13.07.16_83170caa
WhatsApp Image 2023-09-28 at 16.03.40_99acd2fb
WhatsApp Image 2023-11-01 at 07.45.03_4ef58cb6
WhatsApp Image 2023-11-01 at 07.45.03_5849a3b7
PHOTO-2023-10-27-14-10-45 (5)
thumbnail_PHOTO-2023-10-13-11-45-18
WhatsApp Image 2023-09-23 at 11.54.33
IMG-20231101-WA0015
IMG-20230927-WA0008
IMG-20230905-WA0001
PHOTO-2023-11-13-12-56-39
WhatsApp Image 2023-10-31 at 14.07.47_e31f7ece
WhatsApp Image 2023-10-31 at 09.56.58_702c5f3a
PHOTO-2023-11-01-15-21-09 (4)
PHOTO-2023-10-17-08-48-41
IMG-20231031-WA0007
IMG-20230905-WA0012
AET 1
WhatsApp Image 2023-11-01 at 13.07.16_83170caa
WhatsApp Image 2023-09-28 at 16.03.40_99acd2fb
WhatsApp Image 2023-11-01 at 07.45.03_4ef58cb6
WhatsApp Image 2023-11-01 at 07.45.03_5849a3b7
PHOTO-2023-10-27-14-10-45 (5)
thumbnail_PHOTO-2023-10-13-11-45-18
WhatsApp Image 2023-09-23 at 11.54.33
IMG-20231101-WA0015
IMG-20230927-WA0008
IMG-20230905-WA0001
PHOTO-2023-11-13-12-56-39
WhatsApp Image 2023-10-31 at 14.07.47_e31f7ece
WhatsApp Image 2023-10-31 at 09.56.58_702c5f3a
PHOTO-2023-11-01-15-21-09 (4)
PHOTO-2023-10-17-08-48-41
IMG-20231031-WA0007
IMG-20230905-WA0012
AET 1
waste-wood-legislative-framework-img

Download Our Technical Update

Download Previous Updates:

News

feature image
PV installation on 10x Academy Schools
by Paul Clark, October 28 2023
Myriad Heat & Power Products Ltd have completed the final commissioning of all 10 schools for an Academy Trust with schools accross the UK. ...
feature image
896kW PV installation on industrial site
by Paul Clark, September 21 2023
Myriad Heat & Power Products Ltd have completed the final commissioning of 896kW roof mounted PV system. The client has a number of large...
feature image
190kW PV installation on wood product manufacturing site
by Paul Clark, August 20 2023
Myriad Heat & Power Products Ltd have completed the final commissioning of 166kW roof mounted PV system. The client is a manufacturer of...