Commercial Biomass - Education - Independent School

Commercial Biomass - Education - Independent School

The System

The biomass boilers were specified to replace 20 oil-fired boilers and associated oil tanks from around the site, in order to route a district heating scheme from one central energy hub.

A pair of 300kW Herz Biomatic boilers were installed over two phases into a purpose-built energy centre plant room that has been designed to suit a third phase should the schools decide to expand.

The boilers also have separate wood chip feed augers so that they can run independently, enabling no need for oil back up. This is also ideal for earning the RHI separately for each boiler. The boilers typically provide in excess of 21,000 litres of hot water to be stored in the system at any one time.

This unique design has afforded the schools the opportunity to upscale their biomass installation and add a third biomass boiler and other renewable technologies as required over the coming years. To date, it is estimated that there is a saving of 140,000 litres of oil per year (an estimated £70,000 per year at 50p per litre of oil). Now an estimated 450 tons (1592m³ much reduced cost).

Overall the Schools have made an impressive estimated annual carbon saving of 288T of CO2.

waste-wood-legislative-framework-img

Download Our Technical Update

Download Previous Updates:

News

feature image
I’m thrilled to be speaking at #IMHX!
by Paul Clark, September 9 2025
Following the success of the UK Warehouse Association 2022 Solar Toolkit, an updated and enhanced edition is being launched this week. This...
feature image
New generation connections are being managed more closely
by Paul Clark, August 14 2025
Navigating DNO Connection Offers: Why Timing is Critical for PV Installations When developing a site for a new photovoltaic (PV) installation, one of...
feature image
Hi-rise PV installation
by Paul Clark, July 15 2025
Myriad have recently completed a new installation of a solar PV system on a high rise block in central London. The panels were fitted to a specialist...