Project Snapshot Sector: Leisure
Location: Southeast England
System size: 163 kWp
PV modules: 359 × Trina 455 W
Inverters: 2 × SolarEdge SE66.6K
Optimisers: 180 × S1000
Mounting: Roof-mounted (mechanically fixed system)
Annual generation: 168,000 kWh
Payback period: 4.5 years
The Client & Requirements The client required a solar PV system that would reduce electricity costs across the holiday park while supplying a meaningful proportion of on-site energy demand. A key objective was to minimise reliance on grid electricity, while supporting the site’s long-term sustainability strategy and carbon reduction goals. In addition, the client was looking for a fully turnkey solution delivered by a trusted provider, capable of managing the entire process from design and approvals through to installation and commissioning. Minimising disruption and internal resource was a priority, so they required a reliable partner who could deliver the project with minimal hassle while ensuring long-term system performance and support.
Key Challenges As the holiday park remained fully operational throughout the installation, with guests on-site, maintaining safety and minimising disruption were the primary considerations. Works had to be carefully planned and sequenced to avoid impacting the guest experience, particularly during peak periods. Strict safety protocols were implemented, including the use of scaffold systems, clearly defined exclusion zones, and controlled access to work areas. Deliveries, lifting operations, and installation activities were coordinated to ensure minimal interference with day-to-day operations, while maintaining a safe environment for both guests and staff at all times.
Solution Delivered Detailed system design and generation modelling to provide an optimal solution
Planning, DNO, and PDR applications
Procurement and installation of Tier 1 PV modules and inverters
Procurement and installation of DC and AC electrical systems
Full commissioning and performance optimisation
Ongoing maintenance and remote generation monitoring
Commercial Outcomes Annual generation: 168,000 kWh |
![]() |