For more than two decades, Myriad has installed tens of thousands of PV panels and battery systems. The benefits of our expertise, bespoke system designs, and dedicated service & maintenance engineers are undeniable.
Myriad delivered a 163 kWp rooftop solar PV installation at Pevensey Bay Holiday Park. This site is geographically favourable for solar due to its location on the south coast, which benefits from comparatively high levels of solar irradiance. The project closely aligns with Park Holiday wider drive to reduce the environmental impact of its estate, with the business focusing on lower carbon emissions, greater energy efficiency and responsible resource management.
The installation combines 359 Trina Solar Vertex S+ 455W modules with an optimised SolarEdge system including 180 SolarEdge S1000 optimisers and SolarEdge SE66.6K Synergy Manager inverters. The system provides 133 kW of total AC power supplied directly into the site and is estimated to generate 168,000 kWh of renewable electricity annually, delivering an estimated CO₂ saving of 30,000 kg per year.
Myriad Heat & Power Products Ltd worked directly with Park Holidays UK Ltd to deliver the complete design, supply, installation, and commissioning of the solar PV system with a full system handover and O&M documentation.
Client: Park Holidays UK Ltd
Solar PV Contractor: Myriad Heat & Power Products